Project Limits

125 Street between Northeast 6 Avenue and Northeast 10 Avenue

Scope of Work

  • Design streetscape enhancements for the corridor
  • Work may include bulb-outs, sidewalk planters, lighting, and bus shelters
  • Secure appropriate funding for construction
  • Permit and install the proposed improvements

Project Timeline

  • Design - June 2016 through July 2019
  • Construction - November 2019 through May 2020

Project Team

Dincer Akin Ozaydin
City of North Miami - City Engineer
Email Dincer Akin Ozaydin

Consultant

Calvin Giordano (CEI)

Contractor

Metro Express