135 Street Force Main Replacement

phase4


Project Quick Facts 

  • Project Overview: The City of North Miami will engage with professional services to the design and construct for the replacement of the 18" force main and construction services. Replace the 18" force main along NE 135 Street from 16 Avenue to Biscayne Boulevard.
  • District: 1
  • Estimated Completion: To Be Determined
  • Funding/Construction Cost: $2,100,000 from Utility Funds
  • Project Status: The project is on hold. Awaiting pending further direction or funding from city staff.
  • Project Contractor: Marcdan
  • Project Consultant: Tetra Tec
  • Contact: Project Manager
    Chuks Okereke, MSCE, City Engineer. Email Chucks Okereke