NE 121 Drainage Project

Project Quick Facts 

  • Project Overview: The project will improve drainage located along N.E. 121st Street, between N.E. 10th Avenue and N.E. 11th Avenue.
  • District: 2
  • Estimated Completion: The project is complete
  • Funding/Construction Cost: $574,122.23 from Stormwater Fund
  • Project Status: The project is complete
  • Project Contractor: Absolute Construction Service, Inc.
  • Project Consultant: N/A
  • Contact: Project Manager
    Chuks Okereke, MSCE, City Engineer . Email Chucks Okereke