Northwest 12 Avenue Force Main Improvements

Project Limits

Northwest 12 Avenue from 95 Street to 125 Street

Scope of Work

  • Inspect the entire line
  • Replace problematic sections of the line

Project Timeline

  • Design - Completed
  • Permitting - Completed
  • Construction - Now through December 2023

Project Team

Chuks Okereke
City of North Miami City Engineer
Email Chuks Okereke

Consultant

CES Consultants

Contractor

Acre Engineering and Construction