Permitting Process

Step1

Submit permit application along with the required documents

Step 2

Pay upfront fees (no cash)

Application Review

Process Based on the scope of work on the application, it is reviewed by the applicable trades in the following order:
Zoning 
Flood 
Landscaping 
Structural 
Engineering 
Mechanical 
Electrical 
Plumbing 
Building
arrow_g1.fw
arrow_g2.fw
If the application is approved by all the required trades:If the application is denied by any of the required trades:
The applicant will receive an email confirmationThe applicant will receive an email notification

Step 3a

Applicant pays remaing fees & submit all required documents

Step 3b

The applicant must address the issues and re-submit the plan to complete the review process
Permit card is issued to applicant

Step 4

Applicant request inspections

Permit is closed after final inspection is passed




arrow_g3.fw